Energy Retrofit Updates [DEV]

November 20th Update

We are excited for our big reveal of the new and improved gymnasium at our first Christmas Bazaar on November 22nd. Visitors will enjoy the comfortable atmosphere of our warm, brightly lit gym.

A new power line is being brought in for the new HVAC system. Pat Norwil, our electrical contractor stepped in to help, with David Harris adding the much-needed update to the lighting.

  • GYM PROGRESS BLURB

  • NEW PORTICO BLURB

  • HVAC SYSTEM BLURB

Gym Progress

New Portico

July 30th Update

After a tremendous effort to ready the space, Phase I of the Energy Retrofit Project began July 1st.

  • Our project manager, Ken Kinzle from Impel Construction keeps things running smoothly.

  • A new power line is being brought in for the new HVAC system. Pat Norwil, our electrical contractor stepped in to help, with David Harris adding the much-needed update to the lighting.

  • The gym walls are readied for insulation-something the building has never had. The interior walls are firred in to prepare for the addition of insulation.

• Key Team Members

• Powerline

• Gym Prep -Volunteers & Board

• Gym Walls